| Kode Tender | 20441170 | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Nama Paket | Pembangunan Gedung Ruang Kuliah Terpadu | |||||||||
| Nama Peserta | PT. PUTRA NANGGROE ACEH | |||||||||
| Tanggal Kirim | 17 Januari 2024 23:11 | |||||||||
| Status Dokumen |
|
| Jenis Barang/Jasa | Satuan Unit | Volume | PPK | Peserta | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Harga Satuan | Total sebelum Pajak | Pajak (%) | Total setelah Pajak | Keterangan | Harga Satuan | Total sebelum Pajak | Pajak (%) | Total setelah Pajak | Keterangan | |||
| PEKERJAAN PERSIAPAN | 1,0 | Rp. 564.327.554,69 | Rp. 564.327.554,69 | 11,0 | Rp. 626.403.585,71 | Rp. 519.557.285,66 | Rp. 519.557.285,66 | 11,0 | Rp. 576.708.587,08 | |||
| PEKERJAAN STRUKTUR | ||||||||||||
| PEKERJAAN BETON LANTAI DASAR | 1,0 | Rp. 2.656.453.496,96 | Rp. 2.656.453.496,96 | 11,0 | Rp. 2.948.663.381,63 | Rp. 2.536.250.651,65 | Rp. 2.536.250.651,65 | 11,0 | Rp. 2.815.238.223,33 | |||
| PEKERJAAN BETON LANTAI I | 1,0 | Rp. 2.539.634.462,65 | Rp. 2.539.634.462,65 | 11,0 | Rp. 2.818.994.253,54 | Rp. 2.425.293.347,79 | Rp. 2.425.293.347,79 | 11,0 | Rp. 2.692.075.616,05 | |||
| PEKERJAAN BETON LANTAI II | 1,0 | Rp. 2.455.454.561,92 | Rp. 2.455.454.561,92 | 11,0 | Rp. 2.725.554.563,73 | Rp. 2.344.782.671,92 | Rp. 2.344.782.671,92 | 11,0 | Rp. 2.602.708.765,83 | |||
| PEKERJAAN BETON LANTAI III | 1,0 | Rp. 1.903.725.041,01 | Rp. 1.903.725.041,01 | 11,0 | Rp. 2.113.134.795,52 | Rp. 1.820.536.343,47 | Rp. 1.820.536.343,47 | 11,0 | Rp. 2.020.795.341,25 | |||
| PEKERJAAN ARSITEKTUR | ||||||||||||
| PEKERJAAN DINDING | 1,0 | Rp. 2.388.461.801,22 | Rp. 2.388.461.801,22 | 11,0 | Rp. 2.651.192.599,35 | Rp. 2.347.069.858,44 | Rp. 2.347.069.858,44 | 11,0 | Rp. 2.605.247.542,87 | |||
| PEKERJAAN PLAFOND | 1,0 | Rp. 729.741.350,56 | Rp. 729.741.350,56 | 11,0 | Rp. 810.012.899,12 | Rp. 705.278.610,00 | Rp. 705.278.610,00 | 11,0 | Rp. 782.859.257,10 | |||
| PEKERJAAN LANTAI | 1,0 | Rp. 1.668.313.815,67 | Rp. 1.668.313.815,67 | 11,0 | Rp. 1.851.828.335,39 | Rp. 1.636.780.235,03 | Rp. 1.636.780.235,03 | 11,0 | Rp. 1.816.826.060,88 | |||
| PEKERJAAN KUSEN, PINTU, JENDELA, VENTILASI DAN AKSESORIS | 1,0 | Rp. 906.488.600,00 | Rp. 906.488.600,00 | 11,0 | Rp. 1.006.202.346,00 | Rp. 831.268.000,00 | Rp. 831.268.000,00 | 11,0 | Rp. 922.707.480,00 | |||
| PEKERJAAN ATAP | 1,0 | Rp. 1.253.072.427,94 | Rp. 1.253.072.427,94 | 11,0 | Rp. 1.390.910.395,01 | Rp. 1.219.707.023,38 | Rp. 1.219.707.023,38 | 11,0 | Rp. 1.353.874.795,96 | |||
| PEKERJAAN PENGECATAN | 1,0 | Rp. 406.994.940,51 | Rp. 406.994.940,51 | 11,0 | Rp. 451.764.383,97 | Rp. 392.967.744,00 | Rp. 392.967.744,00 | 11,0 | Rp. 436.194.195,84 | |||
| PEKERJAAN SANITASI | 1,0 | Rp. 178.950.000,00 | Rp. 178.950.000,00 | 11,0 | Rp. 198.634.500,00 | Rp. 171.890.000,00 | Rp. 171.890.000,00 | 11,0 | Rp. 190.797.900,00 | |||
| PEKERJAAN LANDSCAPE | 1,0 | Rp. 745.181.062,85 | Rp. 745.181.062,85 | 11,0 | Rp. 827.150.979,76 | Rp. 725.344.536,12 | Rp. 725.344.536,12 | 11,0 | Rp. 805.132.435,09 | |||
| PEKERJAAN FASCADE BANGUNAN | 1,0 | Rp. 1.064.409.086,40 | Rp. 1.064.409.086,40 | 11,0 | Rp. 1.181.494.085,90 | Rp. 1.026.910.718,21 | Rp. 1.026.910.718,21 | 11,0 | Rp. 1.139.870.897,21 | |||
| PEKERJAAN LAIN-LAIN | 1,0 | Rp. 147.098.000,00 | Rp. 147.098.000,00 | 11,0 | Rp. 163.278.780,00 | Rp. 148.540.000,00 | Rp. 148.540.000,00 | 11,0 | Rp. 164.879.400,00 | |||
| PEKERJAAN MEKANIKAL | ||||||||||||
| PEKERJAAN PLUMBING | 1,0 | Rp. 352.884.700,00 | Rp. 352.884.700,00 | 11,0 | Rp. 391.702.017,00 | Rp. 357.897.650,00 | Rp. 357.897.650,00 | 11,0 | Rp. 397.266.391,50 | |||
| INSTALASI KRAN TAMAN | 1,0 | Rp. 26.208.000,00 | Rp. 26.208.000,00 | 11,0 | Rp. 29.090.880,00 | Rp. 24.129.000,00 | Rp. 24.129.000,00 | 11,0 | Rp. 26.783.190,00 | |||
| BIO FILTER SEPTIC TANK | 1,0 | Rp. 86.805.000,00 | Rp. 86.805.000,00 | 11,0 | Rp. 96.353.550,00 | Rp. 79.440.000,00 | Rp. 79.440.000,00 | 11,0 | Rp. 88.178.400,00 | |||
| INSTALASI POMPA AIR BERSIH dan KATUP | 1,0 | Rp. 60.770.000,00 | Rp. 60.770.000,00 | 11,0 | Rp. 67.454.700,00 | Rp. 69.620.000,00 | Rp. 69.620.000,00 | 11,0 | Rp. 77.278.200,00 | |||
| PEMASANGAN INSTALASI HVAC SYSTEM LANTAI 1, 2, & 3 | 1,0 | Rp. 1.654.003.800,00 | Rp. 1.654.003.800,00 | 11,0 | Rp. 1.835.944.218,00 | Rp. 1.694.002.000,00 | Rp. 1.694.002.000,00 | 11,0 | Rp. 1.880.342.220,00 | |||
| INSTALASI EXHAUST FAN | 1,0 | Rp. 60.870.000,00 | Rp. 60.870.000,00 | 11,0 | Rp. 67.565.700,00 | Rp. 58.825.000,00 | Rp. 58.825.000,00 | 11,0 | Rp. 65.295.750,00 | |||
| PEKERJAAN FIRE FIGHTING | 1,0 | Rp. 228.700.000,00 | Rp. 228.700.000,00 | 11,0 | Rp. 253.857.000,00 | Rp. 223.637.000,00 | Rp. 223.637.000,00 | 11,0 | Rp. 248.237.070,00 | |||
| PEKERJAAN ELEKTRIKAL | ||||||||||||
| PEKERJAAN PERALATAN \/ PANEL | 1,0 | Rp. 281.000.000,00 | Rp. 281.000.000,00 | 11,0 | Rp. 311.910.000,00 | Rp. 197.000.000,00 | Rp. 197.000.000,00 | 11,0 | Rp. 218.670.000,00 | |||
| PEKERJAAN INSTALASI KABEL FEEDER | 1,0 | Rp. 649.089.097,30 | Rp. 649.089.097,30 | 11,0 | Rp. 720.488.898,00 | Rp. 699.700.000,00 | Rp. 699.700.000,00 | 11,0 | Rp. 776.667.000,00 | |||
| PEKERJAAN ARMATUR LAMPU, SAKLAR & STOP KONTAK | 1,0 | Rp. 436.884.300,00 | Rp. 436.884.300,00 | 11,0 | Rp. 484.941.573,00 | Rp. 312.010.000,00 | Rp. 312.010.000,00 | 11,0 | Rp. 346.331.100,00 | |||
| PEKERJAAN INSTALASI | 1,0 | Rp. 297.300.000,00 | Rp. 297.300.000,00 | 11,0 | Rp. 330.003.000,00 | Rp. 211.810.000,00 | Rp. 211.810.000,00 | 11,0 | Rp. 235.109.100,00 | |||
| PEKERJAAN PENANGKAL PETIR GEDUNG RKU | 1,0 | Rp. 86.489.000,00 | Rp. 86.489.000,00 | 11,0 | Rp. 96.002.790,00 | Rp. 78.769.000,00 | Rp. 78.769.000,00 | 11,0 | Rp. 87.433.590,00 | |||
| PEKERJAAN GROUNDING PANEL GEDUNG RKU | 1,0 | Rp. 53.269.000,00 | Rp. 53.269.000,00 | 11,0 | Rp. 59.128.590,00 | Rp. 41.219.000,00 | Rp. 41.219.000,00 | 11,0 | Rp. 45.753.090,00 | |||
| RAK KABEL | 1,0 | Rp. 72.975.000,00 | Rp. 72.975.000,00 | 11,0 | Rp. 81.002.250,00 | Rp. 62.550.000,00 | Rp. 62.550.000,00 | 11,0 | Rp. 69.430.500,00 | |||
| PEKERJAAN ELEKTRONIK | ||||||||||||
| PEKERJAAN FIRE ALARM TERPASANG | 1,0 | Rp. 218.872.500,00 | Rp. 218.872.500,00 | 11,0 | Rp. 242.948.475,00 | Rp. 298.385.000,00 | Rp. 298.385.000,00 | 11,0 | Rp. 331.207.350,00 | |||
| PEKERJAAN TATA SUARA TERPASANG | 1,0 | Rp. 211.297.500,00 | Rp. 211.297.500,00 | 11,0 | Rp. 234.540.225,00 | Rp. 173.230.000,00 | Rp. 173.230.000,00 | 11,0 | Rp. 192.285.300,00 | |||
| PEKERJAAN INSTALASI CCTV | 1,0 | Rp. 152.353.000,00 | Rp. 152.353.000,00 | 11,0 | Rp. 169.111.830,00 | Rp. 129.600.000,00 | Rp. 129.600.000,00 | 11,0 | Rp. 143.856.000,00 | |||
| PEKERJAAN INSTALASI ACCES POINT | 1,0 | Rp. 37.058.000,00 | Rp. 37.058.000,00 | 11,0 | Rp. 41.134.380,00 | Rp. 35.100.000,00 | Rp. 35.100.000,00 | 11,0 | Rp. 38.961.000,00 | |||
| PEKERJAAN INSTALASI LOCAL AREA NETWORK | 1,0 | Rp. 86.064.000,00 | Rp. 86.064.000,00 | 11,0 | Rp. 95.531.040,00 | Rp. 76.575.000,00 | Rp. 76.575.000,00 | 11,0 | Rp. 84.998.250,00 | |||
| Produk Dalam Negeri (PDN) | Rp. 26.280.000.000,00 | |||||||||||
| Total HPS | Rp. 27.373.931.000,63 | Total Penawaran | Rp. 26.280.000.000,00 | |||||||||